FEMA's three hazard mitigation programs pay to make buildings safer before the next disaster. Only one of them, the Hazard Mitigation Grant Program, lets a private nonprofit apply in its own name.

Updated Reviewed against FEMA's Hazard Mitigation Assistance Program and Policy Guide v2.19 min readBy Bedrock GrantsReport a correction
Short answer

Partly. A private nonprofit can apply directly for the Hazard Mitigation Grant Program (HMGP), which opens only after a major disaster declaration; in Florida it applies through FDEM with a ranking and endorsement letter from its county's Local Mitigation Strategy working group. Flood Mitigation Assistance and BRIC require a government subapplicant, per FEMA's HMA Guide v2.1.

Current Florida status (checked October 16, 2026).FDEM's listed application periods for DR-4794 and DR-4806 closed May 21, 2025 (FDEM NOFA). The periods for DR-4828 and DR-4834 closed July 25, 2025 (FDEM Joint NOFA). Hurricane Isaias is an emergency declaration, EM-3655, and does not authorize HMGP. FDEM's Flood Mitigation Assistance page says its July 13–August 14, 2026 notice-of-interest period is closed. FEMA's BRIC page, updated September 3, 2026, says the FY2024–25 submission period closed July 23, 2026. These sources do not announce the next Florida window.

Three programs, one direct route

FEMA's Hazard Mitigation Assistance (HMA) programs fund projects that reduce future damage from natural hazards. The rules for all three are in the HMA Program and Policy Guide v2.1, which applies to HMGP for major disasters declared on or after January 20, 2025. Who may apply is the first decision.

FEMA hazard mitigation programs and private nonprofit access, checked October 16, 2026
ProgramWhen it opensCan a nonprofit apply itself?Federal share
Hazard Mitigation Grant Program (HMGP)Only after a major disaster declaration that authorizes hazard mitigationYes, as a subapplicant through the state. In Florida, with county LMS working group endorsement.Up to 75%
Flood Mitigation Assistance (FMA)FY2026: activated per flood-related declaration (Swift Current)No. A city, county or other local government must apply.75% generally; more for repetitive-loss properties
Building Resilient Infrastructure and Communities (BRIC)National competition by notice of funding opportunityNo. A state agency, local government or tribe must apply.Generally up to 75%

For FMA and BRIC, the HMA Guide (Part 4, B.3) says private nonprofits "are not eligible subapplicants," but an eligible subapplicant may apply on their behalf. That makes the local government the decision-maker, and its interest in sponsoring a nonprofit's building is the real gate.

HMGP: the program a nonprofit can use

HMGP funding "is available when authorized through a major disaster declaration" (HMA Guide v2.1, Part 2). An emergency declaration doesn't start it. Under 44 CFR 206.434(a), subapplicants include private nonprofits that own or operate a private nonprofit facility as defined in 44 CFR 206.221(e). The organization needs an IRS 501(c) ruling letter in effect on the declaration date, or state documentation of its nonprofit status. FEMA also checks that the facility provides a critical service, such as education or medical care, or an essential social service open to the general public. A private nonprofit school fits the educational category.

The organization doesn't need its own hazard mitigation plan. The jurisdiction where the project sits must have a current FEMA-approved local plan.

Florida's county gate

Florida adds a step that decides most outcomes. FDEM delegates project selection to each county's Local Mitigation Strategy working group (LMSWG), which, in FDEM's words, will "alone determine which eligible mitigation projects will be placed on their project priority list." Under Florida rule 27P-22.007, each application needs an endorsement letter from the working group's Chair or Vice-Chair. The letter must verify that the project appears in the current LMS and state its priority among the county's projects. FDEM's notices say an application without it will be denied, and a separate letter is required for each declaration.

FDEM announces each HMGP cycle with a Notice of Funding Availability in the Florida Administrative Register. The rule gives applicants at least 90 days from the notice, and FDEM sets the exact dates for each disaster. Applications go through FDEM's online portal, and FDEM's notices require the portal access request by 5:00 p.m. on the deadline day.

Houses of worship: an unresolved conflict

Two FEMA documents point in different directions, and a congregation should know both before it spends money on a mitigation application.

  • FEMA's May 3, 2018 policy clarification, issued after the Bipartisan Budget Act of 2018, says a house of worship may be an HMGP subapplicant and that HMA will fund eligible activities for it "including retrofitting and elevation which primarily benefit the house of worship." It applies to major disasters declared on or after August 23, 2017.
  • The current HMA Guide v2.1 lists as ineligible (Part 4, page 49): "Retrofitting facilities primarily used for religious purposes, such as places of worship (or other projects that solely benefit religious organizations)." It allows a place of worship only within an acquisition and demolition or relocation project that benefits the entire community.

The documents do not reconcile this conflict. Read plainly, the current Guide bars a wind or flood retrofit of a sanctuary, while the 2018 memo allows it. Before a house of worship asks its county working group to rank a retrofit, it should ask FDEM's mitigation program staff, in writing, which rule FDEM and FEMA will apply to that building, and keep the answer. A day school or community building on the same campus, used primarily for nonreligious services, may raise a different question; describe the building's actual use when you ask.

Houses of worship are eligible for Public Assistance after a major disaster, under separate rules. See FEMA Public Assistance for private nonprofits.

What HMGP can fund

FDEM's most recent notices (Joint NOFA, DR-4828 and DR-4834) list the eligible and ineligible activities. The ones most relevant to a nonprofit building:

HMGP activity eligibility in FDEM's 2025 notices
EligibleNot eligible
Wind retrofit of an existing structure (openings, roof, shutters)Equipment such as emergency pumps, vehicles and communication devices
Structural retrofit and infrastructure retrofitStand-alone studies, design and planning not tied to a proposed project
Generator for a critical facility, or as an integral part of a larger eligible project; secondary power sourceConstruction of new facilities (Code Plus upgrades to new facilities may be considered)
Safe room for severe wind eventsTree removal, debris removal and other maintenance
Dry floodproofing, elevation and flood risk reductionProjects already in progress

Cost share. FEMA contributes up to 75 percent of the approved project cost, and the subrecipient provides the other 25 percent in cash or eligible in-kind contributions. Budget the 25 percent before you apply. FDEM's notices also describe a Global Match option, which gives credit for state or local government funds committed to similar projects.

Cost-effectiveness. A project must show a benefit-cost ratio of 1.0 or greater using FEMA's benefit-cost analysis, unless it qualifies for FEMA's pre-calculated benefits (HMA Guide v2.1, Part 5). Pre-calculated benefits exist for a short list of project types, including non-residential hurricane wind retrofits and generators for hospitals. Other projects need a full analysis, which takes engineering estimates and loss history, so start collecting damage records and repair invoices from past storms now.

Application and management costs

Pre-award costs

The HMA Guide (Part 3, D.4) allows pre-award costs directly related to developing a subapplication, such as gathering environmental data, preparing the benefit-cost analysis or preparing design specifications, subject to FEMA approval at award. The conditions are strict:

  • For HMGP, only costs incurred after the date HMGP is authorized, generally the declaration date, qualify.
  • Each cost must be a separate line item in the subapplication budget and can't be funded by another award.
  • Applicants that are not selected receive no reimbursement for pre-award costs.
  • In Florida, pre-award costs must be requested in writing with FDEM's signed pre-award request form at submission (FDEM Joint NOFA).

Pre-award costs are incurred at the organization's risk. They are reimbursable only if FEMA awards the project and authorizes the cost.

Subrecipient management costs

HMGP pays subrecipient management costs (SRMC) up to a hard cap of 5 percent of eligible and actual project costs, at 100 percent federal share, as a separate pool outside the benefit-cost analysis (FDEM Joint NOFA). FDEM requires a separate SRMC request form with the application. Under the HMA Guide, pre-award costs designated as management costs, such as developing the application and preparing the benefit-cost analysis, count toward the same 5 percent.

FDEM's SRMC guide lists eligible activities such as progress and financial reports, procurement compliance, reimbursement requests, closeout and record retention. Architecture, engineering, design and construction management are project costs, not management costs.

Procurement rules for consultants

A nonprofit subrecipient must follow 2 CFR 200.318 through 200.327 for every contract charged to HMGP, including applicable pre-award work under FDEM's notices. Competition must be full and open under 2 CFR 200.319. A contractor that drafts specifications or a statement of work for a procurement can't compete for that procurement. Professional fees may not be contingent on recovering federal money under 2 CFR 200.459, and 2 CFR 200.324 bars cost-plus-percentage-of-cost contracts.

The FY2026 FMA Swift Current notice applies the 2 CFR 200.319(b) restriction to contractors that help develop an application, project plan or budget. Federal funds can't pay that contractor for later work unless a compliant competition produced a contract that explicitly covers both development and execution. This condition governs FMA Swift Current. The HMA Guide v2.1 does not state the same extension for HMGP, so an HMGP applicant planning one firm for both stages should get FDEM's written direction before procurement.

FMA and BRIC through a local government

The FY2026 FMA Swift Current notice makes $600,000,000 available through activations tied to flood-related disaster or emergency declarations made between June 1, 2025 and May 31, 2027, including hurricanes. A state qualifies through its National Flood Insurance Program (NFIP) claims history. The notice says FEMA usually confirms eligibility within about 60 days of a declaration, and that each activation's application period has its own deadline. Eligible subapplicants are cities, counties, other local governments, special districts and tribes. The property must carry an NFIP policy and be a repetitive-loss or severe repetitive-loss property, or be NFIP-insured and substantially damaged; eligible work is acquisition, elevation and nonresidential floodproofing.

FDEM's FMA page ran a notice-of-interest period from July 13 to August 14, 2026 and says the application period is not open. BRIC's FY2024–25 round closed July 23, 2026, and the FEMA BRIC page lists only governments and tribes as applicants. For either program, a nonprofit's path is to ask its city or county to sponsor the project.

What to do now

The application periods identified in the status box are closed, and those sources give no date for another Florida window. An organization can prepare without assuming when another notice will appear:

  • Find your county's LMS working group, learn when it meets and how it adds projects to its priority list, and ask how a private nonprofit submits one.
  • Define the project: the building, the hazard, the measure and a written cost estimate. Collect records of past storm damage and repairs for the benefit-cost analysis.
  • Confirm your IRS ruling letter, the facility's use, and the source of your 25 percent share.
  • If you are a house of worship, get FDEM's written answer on the retrofit question before you invest in design.
  • Adopt a written procurement policy and conflict-of-interest standards before you hire anyone whose costs you plan to claim.

For a future HMGP cycle, use FDEM's notice for that declaration to confirm the application period and submission rules.

Frequently asked questions

Can a mitigation grant pay for work we've already started?

No. FDEM's HMGP notices list projects already in progress as ineligible, and construction may not begin until the state-subrecipient contract is signed and environmental review is complete (FDEM Joint NOFA, DR-4828 and DR-4834). The HMA Guide also makes ground disturbance or construction before FEMA approval ineligible.

Is a security upgrade a mitigation project?

No. FEMA's hazard mitigation programs address natural hazards such as wind, flood and wildfire. Security hardening against attacks is funded through other programs, chiefly the Nonprofit Security Grant Program.

Sources

  1. FEMA, Hazard Mitigation Assistance Program and Policy Guide, Version 2.1 (effective January 20, 2025), FDEM-hosted copy
  2. FEMA, Hazard Mitigation Assistance guidance
  3. FEMA, Policy Clarification: Project Eligibility for Private Nonprofit Houses of Worship under HMA (May 3, 2018)
  4. FDEM, Hazard Mitigation Grant Program
  5. FDEM, Joint Notice of Funding Availability, HMGP DR-4828 and DR-4834 (Helene and Milton)
  6. FDEM, Notice of Funding Availability, HMGP DR-4806 (Debby), February 17, 2025
  7. FDEM, Notice of Funding Availability, HMGP DR-4794
  8. Florida Administrative Code, Chapter 27P-22, Hazard Mitigation Grant Program
  9. FDEM, HMGP Subrecipient Management Cost Request how-to guide
  10. FEMA, FY2026 Flood Mitigation Assistance Swift Current NOFO (DHS-26-MT-144-000-99)
  11. FDEM, Flood Mitigation Assistance program
  12. FEMA, Building Resilient Infrastructure and Communities (updated September 3, 2026)
  13. OpenFEMA, Disaster Declarations Summaries (Florida)
  14. FEMA, Florida Hurricane Isaias (EM-3655-FL)
  15. 44 CFR 206.434, Eligibility (HMGP)
  16. 44 CFR 206.221, Definitions (private nonprofit facility)
  17. 2 CFR 200.317 through 200.327, Procurement standards
  18. 2 CFR 200.319, Competition
  19. 2 CFR 200.324, Contract cost and price
  20. 2 CFR 200.459, Professional service costs

Not sure which security grants fit?

Tell us about your organization. We’ll give you a free preliminary read on which security grants may fit, what they could pay for, and what applying involves. The administering agency makes the final eligibility call.